Big Branch 2 regional sewer pump station

Apex

Summary

A $17.5M pump station will serve the 3,700-acre Big Branch basin, letting the town retire three aging pump stations and meet its interbasin transfer obligations. Construction runs about 18 months, finishing around August 2028.

At a glance

Total mentions
1
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.

Impact analysis

💰Financial impact

$17.53 million, funded through the 2023-2024 CIP, with $1.1 million saved through value engineering.

✅Who benefits

Residents and developers in the Big Branch basin get reliable sewer capacity and lower long-term operating risk.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Apex

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.