Summary
A $17.5M pump station will serve the 3,700-acre Big Branch basin, letting the town retire three aging pump stations and meet its interbasin transfer obligations. Construction runs about 18 months, finishing around August 2028.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
$17.53 million, funded through the 2023-2024 CIP, with $1.1 million saved through value engineering.
Residents and developers in the Big Branch basin get reliable sewer capacity and lower long-term operating risk.